Baseline designs for schools
The baseline design for schools guidance was developed by The Education Funding Agency (EFA) in response to a recommendation in the Review of Education Capital, in April 2011 which identified the requirement for a set of standardised drawings and specifications that could be used across a variety of educational institutes. The EFA is an executive agency, sponsored by the Department for Education (DFE).
The guidance documents are aimed at contractors, local authorities, school promoters and school building teams, along with other interested parties including governing bodies and leaders of schools. They are suitable for both primary and secondary schools.
They provide assistance with good practice design for the Priority School Building Programme (PSBP) and are detailed enough to enable environmental modelling and to establish building costs. The PSBP was established in 2011 to address the needs of those schools in the worst condition that required urgent repair. The programme is centrally managed and procured by the Education Funding Agency.
To deliver 'the maximum benefit for schools', the cost per square metre in the guidance has been reduced to £1113/m2 (excluding external works, fees and certain circumstances). The area has also been reduced, according to the guidance, 'without compromising the educational facility'. In secondary schools, teaching spaces and non-teaching areas are within the same minimum limits as before, but in primary schools the ICT room has been omitted, due to the widespread use of portable ICT equipment in classrooms.
There are a suite of designs available together with associated drawings and technical analyses:
- Baseline design: 105 place primary school with a 26 place nursery.
- Baseline design: 180 place primary school with a 26 place nursery.
- Baseline design: 210 place primary school with a 26 place nursery.
- Baseline design: 240 place primary school with a 26 place nursery.
- Baseline design: 600 place secondary school.
- Baseline design: 630 place primary school.
- Baseline design: 1,120 place primary school.
- Baseline design: 1,200 place secondary (practical specialism).
- Baseline design: 1,200 place secondary (academic specialism).
- Baseline design: finger-block 1,200 place secondary school.
- Baseline design: 1,200 place secondary (music and sports).
- Baseline design: superblock 1,200 place secondary school.
- Baseline design: 1,850 place secondary school.
[edit] Related articles on Designing Buildings Wiki.
- Building Bulletin 93: acoustic design of schools.
- Building Schools for the Future.
- Free schools.
- Priority School Building Programme.
- RIBA client adviser.
- Special educational needs: an analysis of the necessities for inclusion
[edit] External references
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February